ArcelorMittal, Mitsubishi Heavy Industries (MHI), BHP and Mitsubishi Development (MDP) have completed the first phase of a carbon capture trial at ArcelorMittal's integrated steelmaking site in Gent, Belgium, capturing more than 90% of the CO2 contained in blast furnace gas at pilot scale.
The campaign covered more than 4,500 hours of operational testing and used MHI's Advanced KM CDR Process to treat a proportion of the blast furnace off-gas. According to the partners, the results supply the operational and engineering data needed to assess a future full-scale installation on the Gent blast furnace.
Assessments based on the trial data indicate that applying the technology at full scale to the pre-combustion blast furnace off-gas could reduce CO2 intensity at the Gent site by up to 24%. Extending capture across multiple emission points in the plant could, the partners say, support progress toward near-zero emissions intensity.
Demanding gas conditions
Blast furnace off-gas carries dust, sulfur-containing compounds and other contaminants, making it a difficult stream for capture equipment. MHI said the campaign showed its process can run under those conditions while producing data for commercial-scale design work.
The off-gas holds significant concentrations of both CO2 and carbon monoxide. Only CO2 was captured in this phase; the remaining carbon, in the form of CO, can still be used for power and heat generation elsewhere on site, with CO2 released when it is burned.
Phase 2 turns to the reheating furnace
The second phase will broaden capture across several emission points, starting with flue gas from the hot strip mill reheating furnace, which heats thick steel slabs to the temperature required for rolling. That furnace is fired with a blend of by-product gases — coke oven gas, blast furnace off-gas and basic oxygen furnace gas — together with natural gas, giving the partners a post-combustion capture point with a different, more dynamic flue-gas profile.
Results from phase 2 are expected to inform updated engineering and deployment studies for full-scale applications, and to show how capture can be integrated across multiple processes within an operating integrated steelworks.
Partner roles and reaction
ArcelorMittal is hosting the trial at Gent. MHI supplies the Advanced KM CDR Process and leads carbon capture process engineering and technical evaluation. BHP and MDP, which supply high-quality steelmaking raw materials to ArcelorMittal's European operations, are funding the work.
Frederik Van De Velde, CEO of ArcelorMittal Belgium, said the first stage had improved understanding of how carbon capture can be incorporated into existing steel plants, and described scaling up the needed technologies as the vital next step.
Tatsuto Nagayasu, senior vice president and head of CCUS at MHI, called the 4,500-hour campaign and the above-90% capture rate an important milestone for applying the company's technology in steel, and said the hot strip mill phase would strengthen understanding of integrating capture across multiple emission sources.
Dr. Ben Ellis, vice president of marketing sustainability at BHP, said the results demonstrate the abatement potential of the blast furnace and integrated steelmaking route, noting that around 70% of global steel production currently comes from blast furnace steelmaking and that the route is expected to remain important for decades.
Tadashi Mizuno, managing director and CEO of MDP, said the phase 1 results strengthened confidence that carbon capture on blast furnace gas could be a viable emissions-reduction pathway, alongside energy efficiency improvements and the use of high-quality raw materials.